Tuscaloosa Tennis Center (TTC) will be expanded from its existing size to better serve the Tuscaloosa community and attract larger tournaments and events. The planning and design process began in the summer of 2022 with Chambless King being selected for professional design services.


Jaycee Park, as part of this work, will receive improvements to the existing restroom, walking trail, and large shelter pavilion. Additionally, lighting and security cameras will be added throughout the entire park to increase safety.


Currently, the facility includes three indoor courts, six outdoor clay courts, and four outdoor hard courts. TTC is operated by Tuscaloosa County Park and Recreation Authority and offers programs for all ages throughout the year. In addition, it hosts tournaments and events and collaborates with other organizations to engage the community in the game of tennis. 

Goals and Impact
  • Provide more recreational opportunities for residents 

  • Improve existing offerings at Jaycee Park

  • Enhance lighting and security features 

  • Attract tournaments and events that cannot be held at the existing facility

  • Expand capacity for youth programs, collaborations, and memberships

Project Updates
Timeline

Hover to see details

Key Milestones & Events
Completed:
  • Hired Chambless King for professional design services in July 2022

Up Next:
  • Complete design and cost estimation process

Project Materials
Financial Information
Costs

Cost Summary

?

Spent:

$186,444

Approved:

$1,090,851

Budget:

$11,200,000

hide cost details

Spent: The amount paid on this project to-date.​

Approved: The amount that has been approved by the City Council to be spent for a specific contract or purpose on this project. In city accounting terms, this is spent + encumbered.

Budget: The total amount of money that the City expects to be spent to complete this project. This amount is only finalized once sufficient planning on the project has been completed.

Cost Details

Elevate Tuscaloosa Fund: City funds dedicated to Elevate Tuscaloosa which are allocated to this project.

Other City Funds: City funds from non-Elevate Tuscaloosa sources allocated to this project.

External Funding: Amounts from sources outside of the city, such as grants, or donations from citizens or private companies.

Overall Funding

Funding Summary

?

Elevate Tuscaloosa Fund:

$11,200,000

Other City Funds:

$0

External Funding:

$0

hide funding details

Funding Details