Kaulton Park
Updated Jun 27 2023
Latest News
Summary
Improvements to this neighborhood park are expected to include a variety of amenities, lighting, and security features. Among these are a new playground, public Wi-Fi, park lighting, security cameras, and upgrades to the ball field where kids gather for games. A new, large pavilion will provide not only sheltered seating for the community to gather and host events, but also modern restrooms.
Kaulton Park is comprised of four acres arranged in a unique semi-circle shape. The property was part of the original "Kaulton" planned community founded in 1912 that included Kaul Lumber Company, residential housing, and commercial establishments that served the area. The site was deeded to the city in 1972 and is designated as a public park.
Goals and Impact


Provide recreational opportunities for families
Improve a community gathering space
Enhance lighting and security features
Project Updates
Timeline
Hover to see details
Key Milestones & Events
Completed:
Up Next:
Project Materials
Financial Information
Costs
Cost Summary
Spent:
$0
Approved:
$93,070
Budget:
$1,750,000
hide cost details
Spent: The amount paid on this project to-date.
Approved: The amount that has been approved by the City Council to be spent for a specific contract or purpose on this project. In city accounting terms, this is spent + encumbered.
Budget: The total amount of money that the City expects to be spent to complete this project. This amount is only finalized once sufficient planning on the project has been completed.
Cost Details
Elevate Tuscaloosa Fund: City funds dedicated to Elevate Tuscaloosa which are allocated to this project.
Other City Funds: City funds from non-Elevate Tuscaloosa sources allocated to this project.
External Funding: Amounts from sources outside of the city, such as grants, or donations from citizens or private companies.
Overall Funding
Funding Summary
Elevate Tuscaloosa Fund:
$1,500,000
Other City Funds:
$250,000
External Funding:
$0
hide funding details